Correct installation sequence of mobile shelving
Installation has a great impact on the life of the archive dense frame, installation to find a regular manufacturer, the following is the steel office furniture manufacturer WOMA simple explain the steps of the installation of dense frame, the correct installation is beneficial to the use of mobile rack shelving cabinet.
mobile shelving in loading and unloading or transportation must avoid the situation of bump and bump, can not be rough loading and unloading, installation must pay attention to gently take gently, so as not to lead to dense frame surface damage, and once such a situation occurs, then it will lead to cabinet rust

mobile shelf

library furniture
Archive intensive frame installation is the first step of laying rail, rail laid level can make intensive frame in the level of mobile more portable, for not quite flat ground need in the ground rail below matting pad iron.
The 2nd step places chassis, want to place the chassis that completes beforehand only to go up in ground track can.
The third step is to fix the column. Be sure to tighten the screws of the column and the site. If the screw is not firmly screwed, the whole dense frame may shake.
The fourth step is to install the side plate and debug the rocker. The transmission device of the dense frame is transmitted to the site through the chain disk by shaking the rocker. The three are closely connected and need to be adjusted to achieve lightness and flexibility.
The fifth step is to install the hanging plate, partition board, book strip and roof. This step only needs to install to the specified location.
The sixth step is to install and debug the door panel.
Step 7 Install dust plates, sealing strips, and catalog plates. The front of these two small things play a very big role, can effectively dust, rat. Catalog cards make it easier to find the files you need.
The last step is the overall inspection and acceptance, if there is any installation or use of the problem timely correction. If a fault occurs, do not deal with it by yourself, which may lead to more serious situations. When placing the dense frame, we must pay attention to the wall and the ground to keep a certain distance, because this situation will increase the probability of moisture.
As long as the above steps are installed in place, the dense frame is absolutely convenient to use. If individual places are not installed in place, the link part may be deformed for a long time. If the transmission device is not installed in place, the dense frame can not be used for long time and will fail.